TM 5-3820-205-10-1
Figure 15. Feeder relief chute extension, installed position.
m. Open the main control panel door and move the circuit breakers to the ON position (figs. 16-18).
n. Install the air cleaner channel holding bracket. Position the air cleaner extension tubing with clamps. Install
the precleaner (fig. 54).
10. Movement to a New Worksite
a. Remove all aggregate material from the conveyor belts, hoppers, and crusher.
b. Disconnect the main power cable and the short main power cable from the power source, and disconnect all
cables from the control panel in reverse of the instructions on figures 11 and 12.
c. Remove the feeder jumper cable from the feeder motor in reverse of the instructions on figure 13.
d. Install the feeder jumper cable on the reel in reverse of the instructions on figure 10.
e.. Remove the ground cable in reverse of the instructions on figure 8.
f. Install the main power cable on the reel in reverse of the instructions on figure 9 and stow the short main
power cable in the toolbox.
g. Remove other components of the crushing and screening plant clear of the roll crusher.
h. If the dolly has been removed, report to organizational maintenance for dolly installation.
i Raise the roll crusher with the jacks and remove all cribbing.
j. Remove and stow the landing jacks and wheel chocks in reverse of the instructions on figure 4. Stow the
landing jack pads in the toolbox (fig. 1).
k. Remove the feeder chute extension and stow the extension in reverse of the instructions on figure 14.
l. Remove roll crusher electric cable connector and airbrake hoses from the toolbox and install on roll crusher
(fig. 2).
TA507886
15