Figure 13. Head belt scraper, installed view.
j.
Remove the jaw pit guard and chain from the toolbox (fig. 1) and install on operator's platform (fig. 14).
k.
The vibrating screen for the jaw crusher is available with ) in. mesh or X in. mesh. Should the screen that is
installed in the jaw crusher be of the wrong mesh for initial operation, refer to paragraph 73 for screen removal and
installation.
I.
The jaw crusher jaws can be adjusted from 1X-3 in. opening. The opening is measured between the jaws from
the lowest point in the valley between the ridges on one jaw to the highest point on the ridge of the opposite jaw. The
measurement must be taken at the lower opening between jaws. To adjust the jaws, refer to paragraph 72.
m.
Remove the ground rod assemblies from the toolbox (fig. 1) and assemble the rod. Attach one end of the
ground cable to the clip on the rod, and the other end of the ground cable securely to a point on the jaw crusher frame
(fig. 15).
Figure 14. Operator's platform guard rails, installed view.